Wolfe Field Construction Costs
Preliminary Project Budget for Remaining Work
Phase Two - Bleachers, Press Box, and Soft Costs:
- Underground Utilities - $50,250
- Paving - $85,500
- Approach for Gates - $10,000
- New Gates - $1,000
- Batting Complex Foundation - $6,000
- Fencing - $7,280
- Bullpen Warm-up Mounds - $2,000
- Bleacher Foundations - $12,000
- Bleachers - $250,295
- Idaho State User Tax on Bleachers - $15,017
- Name Plates - $3,250
- Signage Backing - $20,000
- Press Box/Concession - $135,000
- Electrical - $30,000
- Geotechnical Report - $7,500
- A/E Fees - $87,000
- Legal/Administrative Fees - $5,000
- Project Testing - $2,500
- Water Connection Fees - TBD
- Sewer Connection Fees - $24,900
- Idaho Power Engineering - $3,500
- Idaho Power Connection - $10,000
- Telephone ServiceTBDSignage - $25,000
- Builder's Risk Insurance - $15,000
- Survey Work - $3,000
- Reproductions (Bidding and Construction Drawings and Specifications) - $15,000
- Building Permit Fee - $70,000
Phase Total: $895,000
Phase Three - Indoor / Outdoor Batting Complex and Storage:
- Pre-Engineering Building - $41,300
- Building Erection - $20,000
- Finishing Work - $20,000
- Special Construction (Cages) - $2,700
Phase Total: $ 84,000
Phase Four - Stadium Entrance:
- Masonry (w/ Wrought Iron Fencing) - $155,400
- Landscaping - $12,000
Phase Total: $167,400
Phase Five - Lighting, 1st Base Bleachers, and Restrooms:
- Underground Utilities - $6,750
- Site Lighting - $353,688
- Restrooms - $80,000
- Contingency Fee - $212,170
Phase Total: $652,607
Total Cost of Project: $ 1,800,000